Bump Testing a GX-2009 50
13. After the fresh air purge is complete,
If the bump test passes, the following window will open indicating that. The
BUMP T LED will be solid green. Click OK to return to the main program
window. The BUMP T LED will turn off.
Figure 36: Bump Test Passed
The GX-2009 will automatically be shut off 20 seconds after a successful
bump test.